CompTIA Security+ (SY0-801) · Section 3 of 36

Free Change Management practice questions

10 free SY0-801 questions on Change Management, each with a full explanation — no account needed. This section sits in the Security Foundations part of the exam. Answer every question to see your score, then read the lessons below for anything you missed.

SY0-801
Exam
10
Questions
4
Lessons
0 / 10 answered
Q1 · 1.2

What is the primary role of a change advisory board?

Q2 · 1.2

A technician renews an internal web server's certificate by following a documented procedure that the CAB pre-approved for exactly this task. What kind of change is this?

Q3 · 1.2

A request to replace a branch office's firewall reaches the CAB with passing test results but no backout plan. What should the CAB do?

Q4 · 1.2

File integrity monitoring alerts that the configuration of an edge router changed at 01:30 on Sunday. What should the analyst do FIRST?

Q5 · 1.2

During an approved Saturday change, administrators run a discovery scan across the server subnet. The SOC treats the scan as an attack and isolates the subnet, halting the change. Which step was MOST likely missed?

Q6 · 1.2

A retailer is in its holiday change freeze when a vendor releases a routine patch for its web servers. The patch fixes a flaw with no known exploitation. What should happen?

Q7 · 1.2

A patch for 4,000 workstations has passed testing in staging. Which deployment approach BEST limits the damage if staging missed a problem?

Q8 · 1.2

After a load balancer firmware upgrade, a third of customer sessions drop at random and nobody can explain why. The old firmware ran without problems, and the tested backout takes 30 minutes with two hours left in the window. What is the BEST course of action?

Q9 · 1.2

An impact analysis for patching an internet-facing VPN appliance describes the expected downtime in detail but says nothing about the risk if the patch is postponed. Why is this a problem?

Q10 · 1.2

A maintenance window runs from 01:00 to 05:00. A proposed change takes 2.5 hours to implement, and its tested backout takes 2 hours. What is the MAIN scheduling problem?